New World Newton Carpark Topping
The Conslab Extend team recently completed this car park repair project for BBR Contech at New World Newtown.
The Conslab Extend team recently completed this car park repair project for BBR Contech at New World Newtown.
Our works included installation of 2,600m2 of Sika Top Deck, and Dynamic Crack Bridging System which together with the FRP that BBR Contech installed, will provide the client with an upgraded car park that will last for years to come.
The work was carried out in three stages by our team of approved applicators to minimise disruption as the car park remained open.
A great project for the team that involved many moving parts, long hours, and a dedicated team!
Key Stats
2022
BBR Contech
Wellington